Holiday Delivery Schedule 2023

Lux Garden, Solar Items, Reefe Pumps

  • Orders placed from Fri 22-Dec-2023 will be shipped from Wed 27-Dec-23.
  • Warehouses closed on Mon 1-Jan-2024.
  • Warehouses reopen on Tue 2-Jan-2024.

Cast Iron Items

  • Orders placed from Fri 22-Dec-2023 will be shipped on Mon 8-Jan-2024.
  • Warehouse closed from Fri 22-Dec-23 to Fri 5-Jan-2024.
  • Warehouse reopens on Mon 8-Jan-2024.

Concrete Items

Please factor an additional 4 weeks of workshop closure during the Christmas-New Years break.

Due to rising manufacturing costs a price increase will apply to all concrete items from January 2024. Please order before December 31st to secure the current price.

  • Require 8 weeks of build time.
  • Orders placed from Mon 18-Dec-2023 will have build commencing on 22-Jan-24
  • Workshop closed for 4-weeks from Fri 22-Dec-23 to Fri 19-Jan-2024.
  • Workshop reopens on Mon 22-Jan-2024.